CONEXÃO

Where you can connect to the Rede Básica — by substation, with official data

Transmission access became a periodic competitive process (PNAST, Decree No. 12.772/2025). CONEXÃO organizes, by SIN (the national grid) substation: TUST (transmission tariff) by busbar, transformation capacity, injection margins published by ONS, and the progress of Access Seasons — everything with source and date, nothing estimated.

931
Operation Network substations
1.710
mapped busbars
1.305
busbars with TUST 2025/2026
20,3 GW
admitted in the 1st Access Season

1st Access Season 2026 — upcoming milestones

full calendar (in Portuguese) →
  1. 31/08/2026
    Publicação da NT02 (Quantitativos da Capacidade Remanescente do SIN) e do Valor de Referência (VR) por Barramento Habilitado
  2. 04/09/2026
    Início do período de desistência e declaração de MUST mínimo / intenção de participação em todos os produtos (12h00)
  3. 11/09/2026
    Limite para desistência e declarações (12h00)

Search substation

931 substations (showing 15)

SubstationStateVoltagesMain agentTUST
14 DE JULHO RSUHQJRS230 kVCERAN
ABAIARA CEABACE230 kVCHESF
ABAIARA II CEABA2CE230 kVLIGHT MILAGRES I
ABAIXADORA BAABXBA230 / 69 kVCHESF
ABDON BATISTA SCATASC500 / 230 kVETSE
ABUNA ROANRO230 / 138 kVELETRONORTE
ACAILANDIA MAACMA500 / 230 / 69 kVEATE
ACARAU II CEAUDCE230 / 69 kVCHESF
ACARAU III CEAUTCE500 / 230 kVARGO
ACU II RNACDRN230 / 138 / 69 kVCHESF
ACU III RNACTRN500 / 230 kVARGO VI
ADRIANOPOLIS RJSTADRJ500 / 345 / 138 kVELETROBRAS
AGUA AZUL SPAZLSP440 / 138 / 88 kVAGUA AZUL SPE
AGUA VERMELHA SPAGVSP500 / 440 / 138 kVAUREN OPERAÇÕES
AGUAS LINDAS GOALDGO230 / 69 kVEDP GOIAS