Methodology and sources

Permanent rule: invented numbers are fatal. Every output cites an official criterion and source, or declares a gap. The formal distributor document is the connection budget (ANEEL REN 1.000); the market still says “access opinion”.

What we forecast

  • Micro/mini classification (Law 14.300).
  • Connection budget deadlines (REN 1.000 art. 64).
  • Process roadmap and minimum content (arts. 56–69).
  • Reverse-flow trigger and typed alternatives (art. 73) — without predicting your feeder outcome.
  • Exemption hypotheses (art. 73-A).
  • Educational protection bands (PRODIST Module 3, Table 1).
  • Right to studies within 10 business days (art. 78).

Declared gaps (a feature)

  • Residual feeder/transformer capacity.
  • Which art. 73 alternative the distributor will pick.
  • Structural works cost (unless their public tool states it).
  • Local protection settings / service entrance standard.
  • Absolute “will / will not connect” — forbidden in v1.

Sources (accessed 2026-07-18)