Official ANEEL data
TUST (transmission tariff) by busbar — no digging through ANEEL spreadsheets
Look up the Tarifa de Uso do Sistema de Transmissão (TUST) for generation and load by substation, with the tariff cycle and source act. Estimate your EUST from contracted MUST.
1.798 busbars · latest available cycle: 2025/2026 (REH nº 3.482/2025)
Busbars (generation, 2025/2026)
916
Avg. TUST (generation)
R$ 8,22/kW.month
Lowest TUST (generation)
R$ 5,06/kW.month
Highest TUST (generation)
R$ 18,49/kW.month
Sample busbars
How it works
- Nodal: each busbar has its own TUST based on electrical location on the Rede Básica (basic transmission grid). Values in R$/kW.month.
- Generation × Load: the tariff differs by segment; load has peak/off-peak components.
- EUST: the monthly charge is
MUST × TUST. Calculate on the busbar page (in Portuguese).
2026/2027 cycle
The current cycle was homologated by Dispatch No. 2.269/2026 (effective from 01/07/2026). Per-busbar annexes are being integrated from the official source. Meanwhile we show the latest cycle already available: 2025/2026.