MWattpower-sector data

← Tools

DG connection deadlines (MMGD)

Data: July 22, 2026 · REN ANEEL 1.000/2021

Deadlines in Resolução Normativa ANEEL nº 1.000/2021 (ANEEL, Brazil's electricity regulator, Normative Resolution No. 1,000/2021) relevant to micro e minigeração distribuída (MMGD, distributed microgeneration and minigeneration) connections. Only what appears in the cited article is stated; everything else is marked “check the source.”

In the resolution

StepDeadlineArticle
Preliminary budget — microgeneration or no generation, < 69 kV, no works (service drop only, if needed)15 daysart. 64, I
Preliminary budget — microgeneration or no generation, < 69 kV, with system works30 daysart. 64, II
Preliminary budget — other connections45 daysart. 64, III
Review of application documents/informationup to 5 business daysart. 71
Delivery of contracts after preliminary-budget approvalup to 5 business daysart. 84
Connection works — overhead LV < 2.3 kV (all conditions in the item)Counted from budget approval or return of the contracts (art. 88, § 2).up to 60 daysart. 88, I
Connection works — overhead MV up to 1 km (all conditions in the item)up to 120 daysart. 88, II
Connection works — other cases < 69 kV (not covered by I and II)up to 365 daysart. 88, III
Inspection and meter installation — voltage < 2.3 kVup to 5 business daysart. 91, I
Inspection and meter installation — ≥ 2.3 kV and < 69 kVup to 10 business daysart. 91, II
Inspection and meter installation — > 69 kVup to 15 business daysart. 91, III
Inspection report after rejectionup to 3 business daysart. 94

Check the source

TopicDeadlineCross-reference
Deadlines specific to PRODIST Module 3 (detailed MMGD workflow)REN 1.000 refers to Module 3; deadlines not stated in the cited resolution are not reproduced here.check the sourcePRODIST Module 3
Deadline suspensions and extensions (consulting another utility, ONS, permits, etc.)See the official text for the circumstances and effects — they are not summarized as a fixed deadline.check the sourcearts. 64 § 2 and 89

Frequently asked questions

What is the preliminary-budget deadline for microgeneration without works (except a service drop, if needed)?
15 days, under art. 64, I, of ANEEL Normative Resolution No. 1,000/2021.
What is the deadline for inspection and meter installation below 2.3 kV?
Up to 5 business days, under art. 91, I, of ANEEL Normative Resolution No. 1,000/2021.
Where do these deadlines come from?
From Resolução Normativa ANEEL nº 1.000, de 7 de dezembro de 2021 (ANEEL Normative Resolution No. 1,000 of December 7, 2021). Later amendments, such as REN 1.059/2023, may change provisions — check the current consolidated text.

Official source: Resolução Normativa ANEEL nº 1.000, de 7 de dezembro de 2021 (PDF). Later amendments, such as REN 1.059/2023, may change provisions — always check the current consolidated text.